PROJECT TITLE/ LOCATION 
								         Development of Mohamad Bin Zayed City in Fujairah-Phase-1, Construction 1100 Housing Units / Fujairah								       CLIENT/CONSULTANT
									 AECOM/ARAB TEC									  WORK DONE/EXT. OF TIME
									  3%									  START DATE
									 17/04/2017	
									  EXPECTED COMPLETION DATE
									 15/10/2018	
									  DURATION
									18 Months		
									  REMARKS
									Mobilization	
                                    Scope of work
									Road, Sewerage, Storm Water, Portable Water, Irrigation and fire Figthing Networks	
                                    Project Role
									Sub-Contractor	
                                    Number of persons
									250